TO: Middle School Administrators  

FROM: School Leadership and Support  

DATE: October 9th, 2026 

RE: Updated 2027–28 Master Schedule Timeline  

Purpose  

This memo shares the updated timeline for building 2027–28 master schedules for middle schools. The timeline has two goals: to align scheduling information with high schools and allow schools to identify specific needs of the master schedule and apply those needs using an earlier timeline. 

In addition, the earlier timeline for creating a budget, staff report, and build a master schedule will reduce the number of tasks that are due in February 2027. 

Meeting these goals depends on every step being anticipated and planned for well in advance. Please review the full timeline with your counseling team and front office staff, build these dates into your school calendar now, and plan your communication to students and families around each milestone. 

Key Dates at a Glance  

  • Oct. 8, 2026: IT training on electronic course requests; school setup due by Nov. 15.  
  • Oct. 8 – Nov. 15: High school counselors visit feeder schools. 
  • Jan. 5 – Feb. 26: MS counselors visits to feeder schools. 
  • March 1, 2027: Students complete course requests in PowerSchool.  
  • May 27 – 28, 2027: Students leave school with a tentative 2027–28 schedule.  
  • June 7, 2027: Power Scheduler closes for middle schools.  
  • July 15 – Aug. 13, 2027: Student schedule adjustments during registration.  
Date(s)  Milestone  Lead  
Phase 1: Preparation (September – November 2026)  
Oct. 8 – Nov 15th High schools contact feeder schools to reschedule counselor visits. HS and MS Admin 
Oct. 8, 2026  IT trains school administration on setting up electronic course requests in PowerSchool  IT  
By Nov. 15, 2026  High schools complete electronic course request setup  HS Admin  
Nov. 2, 2026  Enrollment projections and FTE allocations completed  Sam Quantz  
Nov. 30, 2026  All requests for new courses completed  MS Admin  
Nov. 30, 2026  Preliminary budgets released (subject to adjustment)  District  
Phase 2: Student Course Requests (November 2026 – January 2027)  
December Communication out to families regarding upcoming counselor visit dates, processes and schedule choice. MS Admin 
Jan. 5 – Mar. 1, 2027  Counselors visit feeder schools. Students complete course requests using the PowerSchool electronic course request system  Students / Counselors  
By Mar. 1, 2027  Counselors enter all paper course requests (paper requests only in certain circumstances)  Counselors  
Phase 3: Master Schedule Build (January – March 2027)  
Jan. 19 – 22, 2027  Master Build Workshop; high schools begin building (subject to Phoenix Learning Systems availability)  HS & MS Admin / PLS  
Jan. – Feb. 2027  Schools build 2027–28 master schedules  MS Admin  
Feb. 3, 2027  Follow-up enrollment projection to determine whether adjustments are needed  Sam Quantz  
Feb. 26th, 2027  Schools make schedule adjustments based on staffing decisions  MS Admin  
Phase 4: Loading (March – May 2027)  
March – Apr. 23, 2027 (5:00 PM)  Load student requests against schedules and make adjustments MS Admin / Counselors  
Mar. 16 – 26, 2027  Master Schedule Load Open Workshop (Phoenix Learning Systems available for a portion)  MS Admin / PLS  
June 7, 2027  Power Scheduler closes for all schools  MS Admin / Counselors  
Phase 5: Finalizing Schedules (May – August 2027)  
May  Communication out to families regarding schedule for upcoming year MS Admin 
May 27 – 28, 2027  Students leave school with a tentative 2027–28 schedule  Schools  
May 28 – June 7, 2027  Counselors adjust student schedules in PowerSchool  Counselors  
June 7, 2027  Power Scheduler closes  IT  
June 8 – July 14, 2027  IT commits schedules and transitions PowerSchool to the new year  IT  
July 15 – Aug. 13, 2027  Students may adjust schedules during the school registration window  Students / Counselors  

Administrator Action Checklist  

  • Assign the master schedule responsibility to one administrator. 
  • Build all timeline dates into the school master calendar.  
  • Send an administrator or designee to the Oct. 8 PowerSchool training.  
  • Reschedule counselor visits to Oct/Nov. 
  • Submit all new course requests by Nov. 30.  
  • Schedule attendance for the Master Build Workshop (Jan. 19 – 22) and the Master Schedule Load Open Workshop (Mar. 16 – 26).  
  • Assign responsibility for each student and family communication checkpoint.  
  • Coordinate with feeder high schools on the 8th grade ClassChoice window (May 12 – 17).  

Communication to Students and Families  

Clear, early communication is the most effective way to reduce confusion. Each school should plan messages at the beginning of this process. High schools will communicate 9th grade information to your students. 

Frequently Asked Questions  

Q: We have already scheduled visits to our feeder middle schools to help incoming 9th grade students. What if those dates don't fit this timeline?  

A: Middle school visits may need to be rescheduled to align with this timeline. Please plan visits so incoming 9th grade students receive support during the course request window (Nov. 16 – Dec. 18, 2026) and, as appropriate, their ClassChoice window (May 12 – 17, 2027).  

Q: Our counselors prefer to complete CCRs with students before entering course requests. Can we continue this practice?  

A: Course requests may be entered before a student's CCR meeting. If the CCR conversation identifies needed changes, the student's requests can be updated afterward. This keeps course requests on schedule while preserving the CCR process.  

Q: How can we complete the schedule on time while still meeting our other responsibilities?  

A: Building the master schedule is a priority and should be integrated into regular work tasks rather than treated as additional work. Counselors are encouraged to meet with their administrators to determine whether any current job tasks can be given a lower priority.  

Q: WIDA scores are not available until May. How do we place English language learners (ELLs) in the correct classes?  

A: Schedule ELL students based on the best information available at the time of course requests. Once WIDA scores are released, review placements and adjust schedules as needed, such as during the counselor adjustment window (May 28 – June 4, 2027).  

Q: Staffing will not be finalized until February. How can we build the schedule without knowing who will fill each position?  

A: Build sections for unfilled or undetermined positions with the teacher listed as TBA. Once staffing decisions are made, update those sections with the assigned teachers. The timeline allows time for staffing-related adjustments in March 2027.  

Questions  

Please direct questions about this timeline to your Area Director or Sam Quantz. Thank you for your partnership in building schedules that serve our students well.  